Public Notice: Paving scheduled for 9/24/2018. Removal of existing pipe to follow.
Don Ramsey, P.E.
Project Engineer
George W. Luft
Design Engineer, Project Lead
Eric M. Roth, P.L.S.
Project Surveyor
- Email: publicworks4u [at] pendoreille.org
- Phone: 509-447-4513
- In person: 625 W. 4th St. Newport, WA
Partners: WSDOT Highways & Local Programs(Support Services)
Federal Highways ($1,700,000.00)
Washington State Salmon Recovery Funding Board ($250,000)
Kalispel Tribe of Indians (Land Donation & Steering, Access)
County Contribution (Unknown at this point)
Anticipated Project Start-Spring 2018
Anticipated Project Completion-Fall of 2018
Project Timeline
- Preliminary design concept: Originally planned to be part of Phase III of the Leclerc South Corridor Improvement
- Design funding awards: Design-2010
- Field surveying of project limits: Fall 2011
- Preliminary design: Winter 2011
- Field stake proposed alignment: Spring Of 2015
- Construction funding award: 2015
- Project bid: Bids were opened in late fall of 2017. NA Degestrom was awarded the contract.
- Project begins: The contractor did some exploratory excavation this week and began to mobilize equipment to the site.
- Paving scheduled: 9/24/2018